A traffic signal and left turn lanes are coming to the intersection of Colorado Highway 392 and Weld County Road (WCR) 35. Recently, the Weld County Board of Commissioners entered into an intergovernmental agreement (IGA) with the Colorado Department of Transportation (CDOT) for the project north of Greeley and south of Eaton.
The traffic signal and turn lanes aim to increase safety and lessen the likelihood of broadside accidents and injuries. The intersection, currently controlled by a two-way stop, sees heavy use. More than 12,000 vehicles travel through it daily.
“We’re excited to see this project moving forward, as it’s one that will help the intersection meet a growing demand,” said Kevin Ross, Weld County Commissioner and Coordinator of Public Works.
Through the IGA, the two will share the cost of the near $4.8 million project. Weld County is contributing over $1.4 million, while CDOT is contributing the rest of the money — nearly $3.4 million through federal Highway Safety Improvement Program funds. In addition to contributing financially, the Weld County Public Works Department has completed the project’s design and right-of-way acquisitions and is close to finishing necessary utility relocations.
“We’re happy to support CDOT on this safety enhancement. It’s one we believe will have a positive impact on those who travel through that intersection every day,” said Scott James, Weld County Commissioner Chair. “We understand every project has a cost, and we’re pleased that CDOT is assisting in this way.”
The start date for the project is not yet known. CDOT will construct, install, and maintain the traffic signal. Weld County Public Works currently maintains WCR 35 at the intersection and will continue to do so after work is complete.